top of page

F10 Notification

When is a construction project 'notifiable'?

01

A project is notifiable if construction work is expected to:

  • last longer than 30 working days and have more than 20 workers working at the same time at any point on the project

  • or exceed 500 person days

02

Do the days include weekends and bank holidays?

Every day on which construction work is likely to be carried out should be counted, even if the work on that day is of a short duration. This includes holidays and weekends.

03

Who notifies?

The Client has the duty to notify a construction project. In practice however, the client may ask someone else to notify on their behalf.

​

Try out calculator below!

Get Great Safety Tips to Your Mailbox. Subscribe.

Thanks for subscribing!

© 2024 by JGH CDM Safety.

07871 935185

  • LinkedIn
  • Facebook
  • Instagram
bottom of page